Sometimes an action is triggered several times per stage

There is a BP
https://sara.1box.link/app/workflow/17/constructor/
There is a stage here
https://sara.1box.link/admin/shop/workflowstatus/257/action/new/
when you move on, after a minute it should be transferred to the stage, and there the process for the products is already created, it is necessary through the action, since it simply knocks out 500 manually, since this is happening slowly.
90% of the time, it works normally, but sometimes it happens that it switches over twice and creates processes twice, how can this be fixed?
Original question is available on version: ua

Answers:

Пятецкий Николай Николаевич
Insiders - OneBox
Personal license
Here is an example
https://sara.1box.link/15330/
02.11.2022, 11:00
Original comment available on version: ua

You can add one more empty stage to which the processes that were already at the specified status will be redirected. This can be done using the action "Switch stage after X transitions to the current stage"
02.11.2022, 11:07
Original comment available on version: ua

Пятецкий Николай Николаевич
Insiders - OneBox
Personal license
added, we will test it, thanks
02.11.2022, 13:36
Original comment available on version: ua

Please join the conversation. If you have something to say - please write a comment. You will need a mobile phone and an SMS code for identification to enter. Log in and comment